Pencaitland road works set to close A6093 in January

Due to planned works to extend a gas main to Glenkinchie and upgrade the road surface, the A6093 at the Tyne Bridge will be closed.

The A6093 at the Tyne Bridge will be closed to road traffic (but open to pedestrians) from January 20th to February 10th.
The A6093 at the Tyne Bridge will be closed to road traffic (but open to pedestrians) from January 20th to February 10th.
Carried out by contractor Fulcrum, information began to emerge earlier this week with the appearance of signs at the eastern entrance to the village explaining some of the details to motorists. The most significant disruption occurs between the 20th of January and 10th of February when the Tyne Bridge will be closed to road traffic but, crucially, it will remain open for pedestrians, cyclists and anyone using a pram or wheelchair.

Outside the actual road closure dates, roads works begin on the 6th of January and are expected to finish by the end of February with most delays expected during rush hour, as work on other parts of the A6093 through Pencaitland will use temporary traffic signals.

Today the Community Council received a more detailed breakdown of what is set to happen and when from Bill Laird, the Road Network Officer at East Lothian Council, which we are reproducing below.

The closure will be from Lempockwells Road at the west end eastwards to the west side of the entrance to Pencaitland Parish Church / Old Pencaitland House where the carriageway widens sufficient for the use of traffic signals.

During the closure the residents of the lodge house of the estate and Dovecot Way will still have access .

Pedestrian access will be unrestricted.

The contractor will also take the opportunity to carry out works at the junction with Lempockwells Road in preparation for the remainder of their programme – this will ensure that they are clear of this junction when the other works commence.

Works are likely to commence in the village week commencing 6th January – under standard 2-way traffic control but with a suspension of parking – Main Road – (Church to crossroads), then after the closure week commencing 10th February on Lempockwells Road (Main Road to Huntlaw Road) and Huntlaw Road (Lempockwells Road to railway bridge at No 45)

EL Road Services will surface the closed section of road week commencing 3rd February – 1 week only this is part of our capital programme of surfacing works and we are taking the opportunity of the road closure to complete the works and reduce the impact on the residents of the village. At this time the works will NOT include anything other than surfacing of the carriageway and re-applied road markings.

Apart from reinstating any excavations Fulcrum will not be undertaking any works on our behalf.

The contractor has also been asked to produce a letter to be issued directly to those properties adjacent to the streets listed and to supply a copy to me so that I can pass it on to you. They have also agreed to consult with the community council, school and bus companies – advance warning signs are already in place.

Where possible I want to make sure that as many people are aware of the works and effect it will have on their daily travel.

Bill Laird

The Community Council has also been contacted by contractors Fulcrum. The company’s Project Manager for this work, John McLuskey, is keen to hear from anyone with specific questions about the planned works which he will endeavour to answer. John can be contacted via email.

Please remember to share this information with any neighbours and friends living locally, to ensure that as many people as possible are aware of the expected disruption in advance.